PROBLEM

This 35 year old apartment complex had an underground parking garage that was leaking. The original waterproofing was a “between-slab” roofing membrane which had failed.

Tenants were forced to build tarp structures over their vehicles to protect them from dripping water. Steel structural materials were at risk because of all the water. The deck surface over the garage, which many of the tenants looked onto, was an eyesore.

DURADEK SOLUTION

The original surface was ground down, and then levelled off with acrylic modified cement.

Duradek was then applied over the entire surface and 6 inches up the wall, where it was mechanically terminated. The outside perimeters were turned over 6 inches as well, which was enough to cover the entire exposed edge of the concrete slab.

View or download the .pdf version of Case History #110 for complete case history with installer details and before and after images.